Skip to main content

Day 2 - Bring in the Crew

My daughter and I went to Lowe's to buy the lumber while the guys cleaned around the area to prepare it, get out the circular saw, etc.  We bought 4X4X8 boards, some stain and a brush to paint the cut ends of the wood.  Fortunately, the boards fit down the middle of our Mazda X5.

Once we unloaded, the guys cut the wood into 4' sections using a circular saw.  We used a plane to mark the 4' mark all the way around the board since the circular saw does not cut all the way through from one side.  Then we laid the boards out so everyone could get a vision of what we were building.  This helped a lot, since they did not understand what I was describing to do!


I then became very disappointed to hear that we needed to wait a few days for the cut wood to dry before we could stain the ends. :(  With only a little more we could do, we used the rough layout to start leveling where the boards would go, leveling each terraced step, and taking dirt out of the middle where our rock fill would eventually go to begin soaking up that rain water.  I want the high side hill along the steps to slope down to meet the terraces, channeling the water into the stairway so that it does not erode and create a gully on the side.  We will work on that embankment after we get the wood in.

My daughter and I, while the guys worked on the leveling, went back to Lowe's to get a few extra boards (to have 7 total boards), 8 rods of 3/8' rebar roughly 18' long, and a 3' width roll of landscape fabric to go under the rock and steps.

One suggestion someone had was to put pavers under the bottom step and treads to make it last longer.  It sounded like a good suggestion, but I had not seen this in any of the online research I did, and it required more digging and leveling, and materials purchase, so we did not do this.

Comments

Popular posts from this blog

Day 3 - The First Step

The First Step Once the cut portions of our wood was finally dry, we were able to begin actually building the steps.  Because we had some heavy rain prior to our being able to put the steps in, we covered the exposed soil with hay from a local feed store so the soil would not get washed away.  Once I got it raked away, hubby roughly leveled the location for the first (bottom) step. Prepping for the bottom step When the area was relatively flat, we placed two of the three timbers from our soon-to-be u-shaped bottom step.  We drilled a screw into the two timbers to keep them together, placed them again, and used play sand and a leveler to get it roughly level. We then took it up and added the third timber to complete the u-shaped step, and then with the play sand and leveler, we got the u-shaped bottom step laying perfect. Getting the screw started Drilling in the screw Use play sand and a leveler to get it level To discourage weeds from growing ...

Day 6 - Top Connections

Top Connections We knew the top would be tricky because the steps would need to connect to an existing concrete walkway that is sloped down.  Although step design should attempt to keep the rise and tread the same for all steps, or at least in a pattern so as not to surprise the walker, we split the top step into two with shorter treads.  This allowed the very top step to act as a leveling "off ramp" from the walkway.  Splitting the last step into two steps also allowed  us to make a sharper curve in the staircase. Connecting to a concrete walkway that is sloped Splitting last step into two shorter steps increases curve We were very happy that the original calculations worked.  Things apparently don't have to be exact for these small steps.  If you are off, you can add a step or split one into two.  My calculations indicated we would need 4 steps that were 4'X4".  It ended up with 3 steps that are 4"X 4" and two steps that are roughl...

Introduction to Building Steps Up a Slope - Assess, Plan and Calculate

After researching how to build steps up a slope or hill, I was unsatisfied with the lack of detail on instructions or the presentation of information in a step-by-step format with related pictures or videos.  This is my attempt to provide that as we build our own steps to solve a drainage issue. I hope you will learn something from my posts, or at least laugh at my mistakes so that your project will go perfectly smooth. Day 1:  The first related project that we tackled was a terraced drainage wall in the front yard.  We put sod above and a rock garden below, and it seems to be working well so far in holding some of the water coming from the rest of the neighborhood to straight under our rental townhouse. The one bad thing about rock gardens in this area is that leaves will get in there and diminish the effect.  Oh, well.  It would have been too soggy for grass. Picture of 1st terrace in front yard complete: On to step 2 - the side yard where a lot of t...